CLC PHYSICAL-FOAMING LINE

100 m³/day CLC Block Production Line

PROCESS ROUTEPhysical foaming · Non-autoclaved curing

CLC / foam concrete block production using physical foaming and non-autoclaved curing. Explore the line visual, production stages, equipment configuration, project examples and installation support.

Get a Production Line Proposal
100 cubic metre per day lightweight block production line engineering layoutOpen full-size layout
ENGINEERING LAYOUT100 m³/day configuration media. Final factory layout and interfaces are confirmed during project engineering.

CAPACITY QUICK INFORMATION

Production-line configuration at a glance

100 m³/dayDesign capacity basis
12.5 m³/hourEngineering calculationNominal planning rate: published daily capacity ÷ one 8-hour production shift.
24Equipment items
Physical foaming · Non-autoclaved curingProcess
PLC control; handling varies by stationAutomation Level
Peeling machine + Single-station rotary vertical cutterCutting System
Engineering layout shown; site adaptation requiredFactory Layout

SOURCE-BACKED CAPACITY DIFFERENCES

What changes in this 100 m³/day configuration

116.35 kW listed totalListed Power
Mould return line × 1 · Complete block mould × 1Mould Quantity / Scope
Peeling machine × 1 · Single-station rotary vertical cutter × 1Cutting Configuration
24 listed equipment rows; final footprint follows the approved site layoutFactory Requirements
Projects planning around the 100 m³/day design basis; shifts, curing and product remain project-specificSuitable Project Scale
Equipment, models, quantities, power and cutting scope are read from this capacity's reviewed BOMDifference vs Other Capacities

SIX-STEP PROCESS

How the production line works

  1. 01

    Prepare & meter

    Feed and weigh the confirmed powder, aggregate and water inputs.

  2. 02

    Physical foaming & mixing

    Prepare the foam with the listed foaming machine and combine it with the metered slurry in the horizontal mixer.

  3. 03

    Pour & mould

    Fill the mould configuration selected for the block product and production capacity.

  4. 04

    Cure & demould

    Use non-autoclaved curing; release the mould when the mix reaches the condition needed for cutting.

  5. 05

    Cut & finish

    Use only the cutting architecture listed for this capacity and variant.

  6. 06

    Transfer & stack

    Move the cut blocks through the specified transfer and palletizing equipment.

COMPLETE EQUIPMENT CONFIGURATION

Complete equipment configuration

Review the equipment for each production stage. Select an equipment image to enlarge it, or open a linked equipment name for more detail.

100 m³/day CLC Block Production Line — equipment configuration
No.EquipmentStageModelDimensionsQty.Unit powerTotal power (kW)
Preparation & metering
1Preparation & meteringHDSL-0018640 × 350 × 1100111 kW11 kW
2Preparation & meteringHDKJ-00118000 × 800 × 80012.2 kW2.2 kW
3Preparation & meteringHDFL-001Ø1310 × H195010.55 kW0.55 kW
4Preparation & meteringHDFL-0011.2 m × 1.5 m × 1.4 m10.55 kW0.55 kW
5Preparation & meteringHDSL-001Ø1100 × H1140 0.9 m³10.55 kW0.55 kW
Physical foaming & mixing
6Physical foaming & mixingHDKWF1-0011150 × 750 × 114017.5 kW7.5 kW
7Physical foaming & mixingHDKY-00117.5 kW7.5 kW
Preparation & metering
8Preparation & metering5000 × 3500 × 15001
Physical foaming & mixing
9Physical foaming & mixingADF-011.5 m³122 kW22 kW
Handling & stacking
10Handling & stackingHDTH-0035600 × 1530 × 310013 kW3 kW
Cutting & finishing
11Cutting & finishingHDOSD1-0013000*1000*2100 (including powered line)122 kW22 kW
Handling & stacking
12Handling & stackingHDTH-0052430 × 1330 × 390017.5 kW7.5 kW
Cutting & finishing
13Cutting & finishingHDSHM1-014250 × 3300 × 3550 (high-precision rotary configuration)118.6 kW18.6 kW
Handling & stacking
14Handling & stackingHDTH-0064800 × 2600 × 380016.2 kW6.2 kW
Moulding, curing & circulation
15Moulding, curing & circulationHDBAS-0011500 × 1080 × 405
16Moulding, curing & circulationTM-00112 m × 1.1 m12.2 kW2.2 kW
17Moulding, curing & circulationHM-00112 m × 1.1 m12.2 kW2.2 kW
18Moulding, curing & circulationJZ-00112 m × 1.1 m12.2 kW2.2 kW
19Moulding, curing & circulationHDZD-0014 m × 1.1 m10.3 kW0.3 kW
20Moulding, curing & circulationHDZD-0024 m × 1.1 m10.3 kW0.3 kW
PLC, electrical & tooling
21PLC, electrical & toolingHDGF-0011300 × 1100 × 4001
22PLC, electrical & toolingHDCBD1-001700 × 500 × 4001
23PLC, electrical & tooling1
PLC, electrical & tooling
24Production equipmentHDCM1-0021220 × 1220 × 630 (complete set)1

PROJECT DELIVERY / TURNKEY SUPPORT

From local materials to an operating factory

A factory proposal connects the project country, raw materials, target product and capacity, product dimensions, factory land, utilities, budget and automation requirement. The service and supply responsibilities are agreed for each project.

  1. 01

    Raw Material Testing

    Evaluate representative samples from the project location before selecting the final process.

  2. 02

    Formula Adjustment

    Adjust the formulation and material ratios against the test results and target product.

  3. 03

    Product & Process Selection

    Confirm product dimensions and the product-specific preparation, forming, curing and finishing process.

  4. 04

    Factory Layout Planning

    Coordinate land, buildings, storage, material flow, foundations and utilities.

  5. 05

    Production Line Customization

    Match capacity, automation, budget, moulds and process interfaces to the agreed factory scope.

  6. 06

    Equipment Manufacturing

    Prepare the agreed machines, tooling and controls against the approved configuration.

  7. 07

    Factory Acceptance

    Check applicable equipment and delivery scope before shipment.

  8. 08

    Packing & Shipping

    Coordinate packing, loading and destination requirements with the project shipping plan.

  9. 09

    Site Installation

    Install and connect the agreed equipment after site conditions are ready.

  10. 10

    Commissioning

    Check machine sequences and trial production with the selected materials.

  11. 11

    Operator Training

    Train operators in safe use, production sequence and routine maintenance.

  12. 12

    After-sales & Spare Parts

    Plan maintenance communication and spare-parts support for the installed equipment.

RAW MATERIAL OPTIONS

Use Locally Available Raw Materials Where the Process Allows

Review local binders, mineral inputs, process water and the physical-foaming system against this capacity-specific CLC configuration.

Test the CLC material system

Review the available binder, mineral input, process water and physical-foaming input against the target CLC block.

Recycled mineral inputs require source-specific sorting, sampling and trial production before they enter the line design.

Tune physical foaming after testing

Test results guide slurry proportions, water ratio, preformed-foam dosage, mixing sequence and mould filling.

The confirmed curing, demoulding and cutting condition then determines mould circulation and downstream handling.

Cement considered as a binder for HENGDE lightweight-product production

Cement

Typical role
Primary binder
Applicable route
CLC physical foaming
River sand considered for CLC block production

River Sand

Typical role
Fine mineral aggregate where grading and cleanliness are suitable
Applicable route
CLC physical foaming
Stone powder sample considered during HENGDE raw-material testing

Stone Powder

Typical role
Fine mineral filler where chemistry, fineness and moisture are suitable
Applicable route
CLC physical foaming
Fly ash used as a mineral raw-material option for lightweight blocks

Fly Ash

Typical role
Mineral powder option subject to source chemistry and performance testing
Applicable route
CLC physical foaming

Sampling and project-specific review required.

Water metering for lightweight-product production

Water

Typical role
Mixing and process water subject to source-quality review
Applicable route
CLC physical foaming
HENGDE physical foaming system for CLC production

Physical Foaming System

Typical role
Preformed physical foam generation and controlled addition
Applicable route
CLC physical foaming
Recycled mineral material prepared for HENGDE project testing

Construction Waste / Recycled Mineral Material

Typical role
Potential recycled option after sorting, sampling and trial production
Applicable route
CLC physical foaming

Sampling and project-specific review required.

CUTTING WASTE RECOVERY

Cutting Waste Settling & Recovery System

A planned collection and settling loop can reduce uncontrolled slurry discharge and recover process water. The exact civil works, pump selection and reuse rate depend on the project layout and tested material system.

  1. 01CuttingCollect cutting water and fine material at the cutting area.
  2. 02DrainageGuide the wet stream through a controlled drainage path.
  3. 03Recovery PitReceive the collected stream in an accessible recovery pit.
  4. 04SettlingAllow suspended solids to separate before water returns to the process-water system.
  5. 05Water ReuseReuse clarified water where the confirmed process and water-quality limits allow.
  6. 06Suitable Fine Material ReuseReturn only tested, compatible fine material at an engineering-approved rate.
LOCAL MATERIAL REVIEW

Send Your Local Material Information Before Final Line Configuration

Raw-material availability varies by country. Send HENGDE your local material information before the final production-line configuration is confirmed.

Evaluate My Local Raw Materials

Representative material photographs: cement, Szlomo Lejb / Sumek101; river sand, Krzem Anonim; fly ash, Ablazejo. Licensed under applicable CC BY-SA / GFDL terms. HENGDE project and testing photographs are identified separately.

PROJECT PLANNING

Planning a Lightweight Block Project?

Tell us your target product, project location and planned output. The selected 100 m³/day configuration is included automatically.

Discuss Your Project

HENGDE VIDEO

Production Line Video

HENGDE production-line video

Watch this HENGDE equipment or production-line video. Final models, dimensions and delivery scope are confirmed for each project.

WhatsAppDiscuss this page